Dpm gypsum

Discussion in 'Subfloor Preparation' started by Andrew70, Mar 15, 2014.

  1. Andrew70

    Andrew70 Well-Known Member

    237
    59
    28
    Is there a dpm to go onto gypsum screed spoke to balls and they don't do one
     
  2. coolevilangel

    coolevilangel Well-Known Member

    4,299
    912
    113
    far as i know there isnt one, gypsum chemically 'cures' out, unlike the std s/c where the moisture leaves etc
    Would be great to have one tho
     
  3. sheene 67

    sheene 67 New Member

    4
    2
    0
    Jdjdbdbdbdbd
     
    Last edited by a moderator: Mar 15, 2014
  4. sheene 67

    sheene 67 New Member

    4
    2
    0
    Ardex DPM1C-moisture readings less than 85%rh (Hygrometer Box) you're good to go, assuming the Anhydrite has been prepared properly.

    All sub-floors chemically cure (including cement/sand screeds) hydration of water is a chemical process. Anhydrite and cement/sand screeds dry at a similar rate (50mm thick) at approx 1mm a day in good conditions (20oC and 65% air rh)
     
  5. Andrew70

    Andrew70 Well-Known Member

    237
    59
    28
    Cheers for that will speak to ardex on monday
     
  6. sheene 67

    sheene 67 New Member

    4
    2
    0
    No problem, remember tho 85% or below
     
  7. Matt

    Matt Well-Known Member Staff Member

    6,328
    1,402
    113