COMPETITION! Win a prize!

Discussion in 'General Flooring Chat' started by Matt, Jun 11, 2010.

  1. Matt

    Matt Well-Known Member Staff Member

    6,328
    1,402
    113
    As this is a RANDOM section we are having a RANDOM comp this month! The forum will be handing out some FREE tools this month for two people only! (dont get too excited as there only small prizes, but it will be a tool you can add to your tool bag)

    THE RULES. - You will need to guess the answer to the random question. You can only post once, YOU CAN NOT EDIT !!! (Once you post you cant change your mind) Also please read down other replys/posts and their guesses. IF you post the same number (answer) as someone else you wont get a prize, the first person will win the price. You will all have untill 18/06/10. Any new members to the forumafter the 11/06/10 can not enter.

    So then, the comp-

    As some know im having building work done. Im having a garage and study/utility built . The total area of the new section (building) is 37 sq'm. The total area including drive way had to have soil removed as it was 1 meter higher than the original building. I have also had the driveway extended into the front garden (7 x 8 meter) that had to have 10-25cm adverage of soil removed.

    The builders estimated i needed 60 tonne of soil removed and they would be here for 2 days digging the footings and lowering the land down to the correct height. TIP- the builders was wrong!


    So questions

    1- what was the totally amount in tonnes that had to be removed?

    2- how many days in total did it take to dig out?

    Get guessing!
     
  2. tedmaced

    tedmaced Well-Known Member

    1,331
    12
    0
    51 Tons and 2 Days , but it depends if it was light or heavy soil :?
     
  3. tedmaced

    tedmaced Well-Known Member

    1,331
    12
    0
    That reminds me of a song..... by Tennesse Ernie Ford... 16 ton and what do you get... another day older and deeper in debt
     
  4. tedmaced

    tedmaced Well-Known Member

    1,331
    12
    0
    Who is FOOTING the bill for this Matt? :lol:
     
  5. admin1

    admin1 Well-Known Member

    474
    8
    0
    45 ton and it took over a week because it started raining, then snowing and then the ground froze solid ;-)
     
  6. tedmaced

    tedmaced Well-Known Member

    1,331
    12
    0
    or you could vulgaminate the shamdooie round the orgitbloid :shock: :eek: :ugeek:
     
  7. Matt

    Matt Well-Known Member Staff Member

    6,328
    1,402
    113

    Is the week a 5 day working week or you saying 7 days?
     
  8. Lambchop

    Lambchop Well-Known Member

    241
    10
    18
    48, 4 days.

    If it takes an hour to dig a hole, how long does it take to dig half a hole?
     
  9. Matt

    Matt Well-Known Member Staff Member

    6,328
    1,402
    113
    so the guesses so far are-


    51 ton & 2 days = tedmaced
    45 ton & 6 days = woodyoulike
    48 ton & 4 days = Lambchop


    Is that it? 3 guesses only? there are tools to be won here!
     
  10. admin1

    admin1 Well-Known Member

    474
    8
    0
    Do you know a builder that considers 7 days a week? ;-) Over a week = 6 - 7 days (and I'm keeping it as vague as any builder would do)
     
  11. Matt

    Matt Well-Known Member Staff Member

    6,328
    1,402
    113

    Thats cheating! only 1 answer please! pick a set number of days.
     
  12. admin1

    admin1 Well-Known Member

    474
    8
    0
    OK, don't bite!

    6 days then
     
  13. hobbit

    hobbit Well-Known Member

    501
    223
    43
    81 tonnes based on topsoil 3-4 days using a machine @approx £25 per hour
     
  14. tedmaced

    tedmaced Well-Known Member

    1,331
    12
    0
    twice as much as the first time you divided it by three take away four multiplied by ten :?
     
  15. flooringman

    flooringman Well-Known Member

    501
    149
    43
    They removed 66 tonnes and it took 6 days.
     
  16. Matt

    Matt Well-Known Member Staff Member

    6,328
    1,402
    113

    2,4,6 days has gone mate.


    pick another number of days!
     
  17. Matt

    Matt Well-Known Member Staff Member

    6,328
    1,402
    113
    The comp is now closed!


    The answer was 300 ton! Thats basically 45 large skips or 15 grab trucks ( what we used )

    That makes 'hobbit' the closest with 81 tonnes.


    It took them 5 days. As no one guessed 5 days but there was a guess either way we will roll on with another comp next month.


    'Hobbit' P.m me your address so we can get you your prize posted out.
     
  18. admin1

    admin1 Well-Known Member

    474
    8
    0
    And how did it become 300 ton?
     
  19. Matt

    Matt Well-Known Member Staff Member

    6,328
    1,402
    113

    a major under estimate!

    the soil was very wet that did not help. then we had the issue of hitting the sewers and had to dig them up, then they hit the main water line that went to other houses and flooded the garden that sent it to mush and the trenches collapsed.

    But mainly down to not estimating the amount to be removed properly.
     
  20. admin1

    admin1 Well-Known Member

    474
    8
    0
    So...... it was more a "hypothetical" question than us trying to work out the maths! (never mind, we'll know for the next competition not to take it toooooo seriously) ;-)
     

Share This Page