Moon Base Alpha II

Discussion in 'Subfloor Preparation' started by Neilydun, Jan 31, 2017.

  1. Neilydun

    Neilydun Well-Known Member

    2,887
    1,223
    113
    I`ve got 600 sq. m of this garbage to sort out
    [​IMG]
    [​IMG]
    2 days of grinding so far
    [​IMG]
     
  2. Rugmunching

    Rugmunching Well-Known Member

    3,861
    673
    113
    :eek: I feel sorry for your lads ha!
    It just looks never ending
     
  3. mjfl

    mjfl Well-Known Member

    6,259
    1,593
    113
    WP_20170131_001.jpg At least you've got space
     
    • Like Like x 1
    • Agree Agree x 1
    • List
  4. Rugmunching

    Rugmunching Well-Known Member

    3,861
    673
    113
    Now thats something I dont miss!
     
  5. Neilydun

    Neilydun Well-Known Member

    2,887
    1,223
    113
  6. mickyr2

    mickyr2 Active Member

    39
    7
    8
    Best jobs u can get those

    Sent from my E5823 using Tapatalk
     
  7. nevertrever2

    nevertrever2 Well-Known Member

    508
    99
    28
    What are you using to grind it down? Your str machine?
     
  8. Glenn H

    Glenn H Well-Known Member

    645
    140
    43
    Was stuck in a warehouse with no radiators and it was full of steel. Damn freezing!!
     
  9. Neilydun

    Neilydun Well-Known Member

    2,887
    1,223
    113
    No mate, Ive did take my str, but just used that to scratch up some existing powerfloat.
    I used one of these, which I think are good machines.
    I probably would have either bought, or hired a 3 phase machine, but there was no 3 phase on site, and if I hired a geni, I would have needed masses of leads.
    [​IMG]
     
  10. alban

    alban Well-Known Member

    52
    4
    8
    What is the floor? Looks like tamped concrete or its gone off before floating.
     
  11. Neilydun

    Neilydun Well-Known Member

    2,887
    1,223
    113
    Concrete floor, loads of water, laid badly !
     
  12. alban

    alban Well-Known Member

    52
    4
    8
    Are you laying something on it all or just trying to get it accepted ?
     
  13. Neilydun

    Neilydun Well-Known Member

    2,887
    1,223
    113
    Polyflor Arena will be going over it, but not the whole area you see in the pictures, just the areas im grinding.
    The other areas will have 1m deck built, 50mm foam the fibre bonded carpet
     
  14. alban

    alban Well-Known Member

    52
    4
    8
    Maybe they thought the whole lot was being decked over !!

    Good luck :)
     
  15. Neilydun

    Neilydun Well-Known Member

    2,887
    1,223
    113
    I`ve done a few like this. They actually come out fine. Will get some pics up once we get installed
     
  16. nevertrever2

    nevertrever2 Well-Known Member

    508
    99
    28
    Is another trampoline park? I take my daughter to one in leeds same set up, jump arena is called did you do that one ?
     
  17. Neilydun

    Neilydun Well-Known Member

    2,887
    1,223
    113
    Yep mate, its another trampoline park. We do the Oxygen Freejumping, and Gravity Force ones.
    We did one in Leeds, on Kirkstall leisure park, which I think is close to Jump Arena. Is that one with the Asda, and the Greggs just round the corner ?
     
  18. Neilydun

    Neilydun Well-Known Member

    2,887
    1,223
    113
    Took a few rolls in today

    [​IMG]
     
  19. nevertrever2

    nevertrever2 Well-Known Member

    508
    99
    28
    I think both parks are quite close to each other both are in the kirkstall area, they look like good jobs to do plenty of area to go at.
     
  20. alban

    alban Well-Known Member

    52
    4
    8
    Hi , that's a lot of Vinyl heavy going even on big areas !!
    Do you put a membrane under it ?
     